It is possible to update the data of components already placed into a project to their most recent version. An outstanding practical example is the reuse of an out of date project to iniciate new ones. However, the saved data on those projects are outdated as well, once the component´s representation or information could have been modified to a new pattern.
Updating a component already place into a project through the converting selection feature
1. Click on the desired components at the graphics area that you wish to update;
2. Click on GE Modify > Convert selection.
Updating the component already placed into a project through the converting all feature.
1. Go to the GE Modify;
2. Click on the Convert all feature;
3. Wait for the converting process.